Tamworth High School

Tamworth High School

Education

  • Building Refurbishment
  • Approx. $2.2 million
  • 12 months - Ongoing

Staged refurbishment of technology workshops, library and hall at an operational Tamworth High School.

Upgrade to the Food Technology, Metal Technology and Wood Technology workshops, along with the Library, Hall and toilet facilities, including the construction of a new plasma cutting shed. Works comprised demolition and strip-out of all nominated areas, supply and installation of appliances and machinery, new joinery and flooring, electrical upgrades, safety upgrades, and mechanical ventilation works incorporating dust and fume extraction to the workshop spaces. As the school remained operational throughout, the program was staged around term schedules to minimise disruption. Cosmetic upgrades were completed throughout, including acoustic panelling to the Hall area.